Four Seasons Water Quality Improvement Project

Print
Share & Bookmark, Press Enter to show all options, press Tab go to next option

Project Overview

The City of Plymouth is working with the Bassett Creek Watershed Management Commission (BCWMC) to construct a water quality improvement project in the area southwest of Highway 169 and Rockford Road (the former Four Seasons Mall area) in order to improve the water quality of the north branch of Bassett Creek (which flows along the east of the site) and to help meet the phosphorus reduction goals for Northwood Lake in New Hope.

The project includes dredging accumulated sediment, fixing failing storm sewer infrastructure, creating two stormwater ponds, and restoring the 3.3 acre wetland in the southeast portion of the site. The project will annually capture at least 110 pounds of total phosphorus and help the city work towards its water quality improvement goals.

The project design plans were reviewed and approved by the BCWMC in 2024. The project has been bid and the contractor will look to start work at the end of January 2025. 

Anticipated Schedule

  • Construction was completed in early winter of 2025. Vegetation management will continue in spring 2026 - fall 2027

Additional Information

Contact

Ben Scharenbroich, Water Resources Supervisor
Plymouth City Hall | 3400 Plymouth Blvd. | Plymouth, MN 55447-1482
P 763-509-5527 | F 763-509-5510 | bscharenbroich@plymouthmn.gov

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Download Acrobat Reader Download Windows Media Player Download Word Viewer Download Excel Viewer Download PowerPoint Viewer