County Road 9 Bridge Over I-494

Print
Press Enter to show all options, press Tab go to next option

eNotify Sign up
Sign up for eNotify email updates about the County Road 9 Bridge Over I-494 project.


Final LayoutFinal Design Rockfork Road and I-494 Project

Project Overview
This project includes plans to replace the County Road 9 (Rockford Road) Bridge over Interstate 494 and improve the intersection. The project is a joint effort of the City of Plymouth, Hennepin County and Minnesota Department of Transportation.

View the final Project Layout (PDF).

Project Status
The city held an open house January 2019 to share draft plans and tentative construction schedules, receive feedback and answer questions.

The project is currently out to bid; bidding documents are available for contractors to review on QuestCDN, bid document #6246826. The bid opening for the project is scheduled for May 1, 2019.

The project is set to begin in May 2019.

Tentative Timeline
Weather permitting, the project will be completed in one construction season. Construction is set to begin in May 2019 and be finished in November 2019. To best accommodate access for nearby businesses and residents traveling the affected area, the project will be completed in three phases. View the Bridge Staging Maps (three phases) and Detour Routes (PDF).

All dates and timing of phases are tentative and weather dependent.

  • Phase 1 – Spring through early summer
    Construction is scheduled to begin in May. Both north ramps will be closed (the ramp from County Road 9 to northbound I-494 and the ramp from southbound I-494 to County Road 9). The bridge will be open to traffic during this phase.

  • Phase 2 – Summer through early fall
    The County Road 9 bridge will be closed to traffic for roughly 120 days. Removal of the existing bridge is tentatively planned in June, which may require the closure of I-494 (nights/weekends). After the completion of this phase, the new bridge will be open to traffic.

  • Phase 3 – Fall through end of year

    During this phase, both south ramps will be closed (the ramp from County Road 9 to southbound I-494 and the ramp from northbound I-494 to County Road 9). While the new bridge will be open to traffic during this phase, motorists may experience lane closures while crews complete the interchange. The anticipated completion date is late November – weather permitting.

Background Information
The existing interchange was built in 1965 without dedicated left turn lanes – and the area has seen considerable development over the past 53 years. As a result, this interchange has experienced daily congestion and has averaged 33 crashes per year over the past five years. The proposed project would improve public safety and reduce congestion by constructing a wider bridge that can accommodate dedicated left turn lanes onto I-494.

Though the bridge is not city-owned infrastructure, the city has partnered with Hennepin County and MnDOT to complete the project.

Open House No. 1 – April 2018
An open house was held April 17, 2018 to display the preliminary plans. City, county and MnDOT staff were on hand to discuss options, receive feedback and answer questions on the proposed project. View the Open House Presentation Boards (PDF).

Open House No. 2 – January 2019
A second open house was held Jan. 16, 2019 to share draft plans for replacing the bridge and improving adjacent intersections, as well as associated traffic detours and construction schedules. Staff from the city, county and MnDOT were available to hear comments, take suggestions and answer questions. The following materials were displayed at the open house:

Contact
Engineering
Plymouth City Hall | 3400 Plymouth Blvd. | Plymouth, MN 55447-1482
P 763-509-5500 | F 763-509-5510 | engineering@plymouthmn.gov

Project Updates
Sign up for eNotify email updates for the County Road 9 Bridge Over I-494 project.