Project Updates - August 7, 2026
- General Updates
- Please note that schedules are weather-dependent. Construction updates will be provided once a week.
- Please reduce/refrain from scheduling deliveries during this intensive phase of the project.
- See Project Phasing Map
- The City’s Contractor will not necessarily be completing phases in sequential order, in an effort to maintain access and undisturbed areas for parking and staging of equipment.
- Phases 1, 1A, & 2 are within the Birch Briar Area
- Phases A, B, & C are within the Highway 55 Frontage Road Area
- Birch Briar Area
- Work by the City’s Contractor/Staff
- Week of Aug 10
- Phase 1: Reinstall mailboxes and install topsoil.
- Phase 1A: Continue site maintenance and turf/tree watering.
- Phase 2: Install concrete curb and driveways.
- Concrete takes 7 days to harden before vehicles can drive on it.
- During the working time, please park vehicles in the Phase 1 area on the odd side (house number) of the road.
- Once the concrete workers are done, you may park near your property on the odd side (house number) of the road.
- Please leave your waste bins at the end of your driveway. The contractor will be coordinating the pickup with the waste haulers.
- Week of Aug 17
- Phase 1: Installation of sod.
- Phase 1A: Continue site maintenance and turf/tree watering.
- Phase 2: Pave the first layer of road asphalt.
- Highway 55 Frontage Road
- Work by the City’s Contractor/Staff
- Week of Aug 10
- Phase B: Install concrete curb and concrete driveways. Concrete takes 7 days to harden before vehicles can drive on it.
- Phase A: Continue utility construction.
- Week of Aug 17
- Phase B: Pave the first layer of road asphalt.
- Phase A: Continue utility construction.
- Phase C: Reclaim (grind up) the existing road pavement and start removals.